How long does the map change process take?

A simple letter of map amendment (LOMA) for a single structure can generally be issued in four weeks. Map changes involving multiple lots or structures can require up to eight weeks. Letters of map revision (LOMR) which requires a change in the base flood elevation or the floodway take approximately 90 days to process. Complex physical map changes may take over a year to process.